Friday, July 25, 2008

Horizon Stage Renovations - Week 3

The demolition phase continues on through week 3:

As we are replacing the previous collapsible seating, the old concrete base needed to be ripped up in order to replace it with a reinforced concrete floor appropriate for the weight of the new permanent fixed concrete risers.

As a bonus, removing the floor in this area also gave us the chance to replace some of the conduit and wiring running through the area.

The lobby has been completely gutted, right down to the concrete floor, and the exposed structure and mechanical in the ceiling.