Thursday, August 21, 2008

Horizon Stage Renovations - Week 4

For week 4, demolition has been completed, and major construction begins.

Now that the floor has been demolished and cleaned out, the ground has been leveled, and new conduit run so that the reinforced concrete base can be poured.



In this photo, the welders are welding new beams into the ceiling so that the catwalks can be suspended from the grid. These catwalks will speed up the lighting hang and focus aspects of the show mounting process.



The dressing rooms have begun to be rewired, for new lighting fixtures, and outlets.